Porter Plaza Storm Sewer Project

On August 9, 2017, there were four (4) proposals submitted and the lowest bid was received from Len Cox & Sons excavating in the amount of $ 289,229.82. The low bid was lower than the budgeted amount of $450,000 and also the latest engineer’s estimate of $363,525.