2017 Water Main Improvements

Water main improvements have been completed on MacGregor Road.  Sanitary sewer repairs have been completed on North Street and the contractor is currently working on completing sewer repairs on MacGregor Road, between Shoals & North.  Once the water & sewer improvements are completed in this segment, the Contractor for the Reconstruction project will begin the roadway Improvements.

Water main improvements on State Street, between Parkview & Daggett,  are also included in the project scope.  This portion of the project includes the connection of the water main along the east side of State Street, and some augured service lines to the west side of State Street.

This project also includes new water main on 9th Street, between Hamilton & Garfield, and on Madison Street, between 8th & 9th.  Utility coordination is currently underway for this portion of the project.