2017 Water Main Improvements

Water main improvements have been completed on MacGregor Road.  Sanitary sewer repairs have been completed on North Street and the contractor is currently working on completing sewer repairs on MacGregor Road, between Shoals & North.  Once the water & sewer improvements are completed in this segment, the Contractor for the Reconstruction project will begin the roadway Improvements.

Water main improvements on State Street, between Parkview & Daggett,  are also nearly completed. The new services have been completed and the contractor is working on abandoning the old water main.

The contractor is currently mainly focused on the water main installation along E 9th street.  Water main construction has been completed between Hamilton & Madison on 9th Street, and the contractor is working their way toward Lincoln.