Construction Updates

State Street (8th Street to 10th Street)
Work in progress with a scheduled completion November/December 2018. Currently working on the west side of State Street.

State Street Re-plumbing
Work in progress. Work being done as part of State Street water main installation. 

State Street Streetscape
Scheduled to begin June 2018. Sidewalks, trees, planter, etc. to be installed following State Street water main project.

Division and Gougar Signalization
Joint effort between IDOT, Will County, and the City of Lockport. Intersection reconstruction and signalization including the addition of turn lanes, curbs, and traffic signals. Scheduled to start June 2018.

7th Street and Washington Reconstruction
Washington Street from 8th Street to 7th Street, and 7th Street from Washington Street to Madison Street. Water main replacement, complete roadway reconstruction with curbs, new storm sewer, and new surface. Scheduled to start June 2018. Scheduled completion October 2018.

8th Street and Valley Reconstruction
8th Street from 9th Street to Summit Street, and Valley Lane from 8th Street to Adams Street. Water main replacement, complete roadway reconstruction with curbs and new surface. Scheduled to start June 2018. Scheduled completion October 2018.

2018 Resurfacing Phase I
Summit Drive south of Division Street, Bunratty Drive north of 151st Street, Arrowhead South subdivision. Grind off and replace surface layer of asphalt. Scheduled to start June 2018. Scheduled completion July 2018.

2018 Resurfacing Phase II
Commerce Street from 10th Street to 12th Street, Second Street from RR Tracks to Canal Street, Lincoln Street north of 9th Street. Grind off and replace surface layer of asphalt. Scheduled to start July 2018. Scheduled completion August 2018.

Well 15
Drilling of new deep well next to water tower on 151st Street near I-355. Installing new well house including ion exchange to remove radium. Drilling scheduled to start July-August 2018. Well house to start 2019.

Oak Avenue Water Main
Install new water main along Oak Avenue from Deerwood Drive to Willow Walk Drive water main to complete loop and remove dead ends to minimize iron and particulate build up. Currently out for bid. Scheduled to start July 2018.

163rd Street Water Main
Install new water main across 163rd St to connect to Sagebrook subdivision to complete loop. Currently out for bid. Scheduled to start July 2018.

GIS Mapping
Collection of locations and public utilities data to provide accurate information and inventory of City owned infrastructure and underground utilities. Ongoing project over next few years.

Gougar Road Water Main
Gougar Road from 163rd Street north to Well 14 (Oak Prairie School) extension / loop connection. Scheduled to start October 2018.

151st Street Water Main
Install new water main along 151st St from MacGregor west approximately 600’. Estimated to start August 2018.

Farrell Rd Multi-Use Path
Install new multi-use path along Farrell Road from Bruce Rd to Division St. Estimated to start late summer / early fall 2018.

2018 Storm Water
Upgrade storm water piping system. Work planned for fall 2018.

Frances Street Storm Water
Install storm sewer to limit flooding along Frances St. Work planned for fall 2018.

Daviess Street Culvert Replacements
Chevron is replacing culverts under Daviess St for 13th St drainage ditch as part of the overall West Side Flood Improvement project. Work is scheduled to start summer of 2018.